ALE’s jacking innovation, Mega Jack 300, has demonstrated its versatility and efficiency by jacking, transporting and installing a 500t pipe rack module over seven-metre high in Kuwait

The pipe rack module, measuring 57m long and 16m high, is the longest and highest module in Kuwait, the strategic heavy-lift service provider stated.

Sarkis Juvelekian, senior project manager, said, “We are delighted to be providing the full onshore heavy lifting solution for one of the largest refineries in the Middle East.”

“Our engineering team have overcome many of the challenges, such as limited clearances with the ability to jack-up high while maintaining stability, all in a safe and efficient manner. Our performance not only illustrates the Mega Jack 300’s ability to handle these modules in the most suitable way, but also the expertise of the team involved,” he added.

The company noted that since the modules are different in their design, this jacking system provided the flexibility, compactness, operating speed, lifting capacity and speed required.

This system is the latest addition to the ALE’s innovation series and the third in the jacking range, supplementing the Mega Jack and Mega Jack 800 systems. It has a capacity of 300t per tower and is much lighter and more compact than the previous models.

ALE’s latest jacking innovation is vital to the successful completion of the KIPIC Al Zour Refinery Project Package two and three, which involves the jack-up, transportation and installation of 188 pipe rack modules varying in size, weight and foundation height.

ALE has completed the transportation, jacking and installation of 1/3 of the modules so far, and ALE’s scope is expected to be completed by September 2019.